Deer Valley Water Treatment Plant Solids Handling Facilities
City of Phoenix, Arizona
Wilson performed CM services and inspections, with assistance from structural and electrical subconsultants. We also provided startup and commissioning services. Job responsibilities included the following:
Administrative services
- Acted as the City’s representative in dealing with the Contractor.
- Certified Contractor’s progress payments.
- Administered project schedule.
- Reviewed shop drawings and test results.
- Provided interpretations and clarifications of the Contract Documents.
Engineering services
- Performed and certified structural and electrical Special Inspections in accordance with City Building Code requirements.
- Provided material testing services (through a Sub-consultant).
- Managed Change Order requests, from the City and from the Contractor.
- Provided cost estimating services.
- Negotiated Change Order prices with the Contractor on behalf of the City, and made recommendations to the City for approval.
- Prepared final Record Drawings based on information submitted by the Contractor.
- Reviewed Contractor’s record drawing information periodically throughout the project.
- Prepared electronic Operations & Maintenance Manual for the project.
Resident services
- Provided full-time on-site resident engineering and inspection staff.
- Reviewed and inspected Contractor’s work.
- Conducted, coordinated, or observed tests as appropriate.
- Interpreted Contract Documents.
- Performed Substantial Completion and Final Completion inspections.
- Prepared and managed punch lists.
- Conducted weekly coordination meetings with City and Contractor.
- Maintained on-site files of all correspondence (in a searchable database).
- Provided monthly status reports to the City.
Special services
- Commissioning services - our personnel operated the plant expansion around the clock for over 90 days during startup, checkout, and commissioning, before turning it over to City operations staff.
- Programming and graphics configuration for a Microsoft Windows (R) - based plant control system.
- Provided process training for City operations staff.
- Monitor training by equipment Vendors for individual equipment.
- Videotaped all training sessions, and transfered to DVD for City use.
- Initiated a formal partnering process with the City and the Contractor.
- Provided warranty follow-up services with Contractor and Vendors, after completion of construction.